Herzog & de Meuron
Project
2019-2026

530_CP_260916_IB_H_4297

530_CP_260916_IB_H_4297

530_CP_260916_IB_H_4180

530_CP_260916_IB_H_4180

530_CP_260916_IB_H_4618

530_CP_260916_IB_H_4618

530_CP_260916_IB_H_000

530_CP_260916_IB_H_000

530_CP_260916_IB_H_3972

530_CP_260916_IB_H_3972

530_CP_260916_IB_H_4342

530_CP_260916_IB_H_4342

530_CP_260916_IB_H_4735

530_CP_260916_IB_H_4735

530_CP_260916_IB_H_3983

530_CP_260916_IB_H_3983

530_CP_260916_IB_H_4173

530_CP_260916_IB_H_4173

530_CP_260916_IB_H_4064

530_CP_260916_IB_H_4064

530_CP_260916_IB_H_4083

530_CP_260916_IB_H_4083

530_CP_260916_IB_H_4124

530_CP_260916_IB_H_4124

530_CP_260916_IB_H_3755

530_CP_260916_IB_H_3755

530_CP_260916_IB_H_4495

530_CP_260916_IB_H_4495

530_CP_260916_IB_H_4404

530_CP_260916_IB_H_4404

530_CP_260916_IB_H_4561

530_CP_260916_IB_H_4561

530_CP_260916_IB_H_4460

530_CP_260916_IB_H_4460

530_CP_260916_IB_H_4416

530_CP_260916_IB_H_4416

530_CP_260916_IB_H_4251

530_CP_260916_IB_H_4251

530_CP_260916_IB_H_3881

530_CP_260916_IB_H_3881

530_CP_260916_IB_H_3946

530_CP_260916_IB_H_3946

530_CP_260916_IB_H_3952

530_CP_260916_IB_H_3952

530_CP_260916_IB_H_4106

530_CP_260916_IB_H_4106

530_CP_260916_IB_H_3895

530_CP_260916_IB_H_3895

530_CP_260917_Group-Movement

530_CP_260917_Group-Movement

Process

Amherst College is located west of Boston and north of New York, at the edge of the Berkshire Mountains. Its historic campus is organized around a central quad, while newer areas developed over time, creating two distinct campus identities. The project uses an existing site to create a new building that brings these parts of the campus together.

530_SI_2406_Map

530_SI_2406_Map

530_CL_0000_Logo-Amherst

530_CL_0000_Logo-Amherst

530_SI_0000_Massachussets

530_SI_0000_Massachussets

530_SI_0000_Amherst-View

530_SI_0000_Amherst-View

530_RFcl_0000_Historical-Campus

530_RFcl_0000_Historical-Campus

530_SI_0000_Campus-Winter

530_SI_0000_Campus-Winter

530_DR_0000_Campus-Plan

530_DR_0000_Campus-Plan

530_DG_0000_New-Center

530_DG_0000_New-Center

The existing Merrill-McGuire building sat at the edge of the hill, creating a barrier to views and movement across campus. Although it was originally adjacent to the quad, its position became increasingly obstructive over time. From the outset, the aim was to avoid repeating this condition and create a more open, modest building in dialogue with the campus.

530_SI_0000_Bird-View

530_SI_0000_Bird-View

530_SI_0000_Merhill-North

530_SI_0000_Merhill-North

530_DG_0000_Modesty

530_DG_0000_Modesty

530_CI_0000_First-Project

530_CI_0000_First-Project

After winning the competition, the client asked us to restart the design. The revised concept combined the student centre with a dining hall, expanding the program from approximately 80,000 to nearly 120,000 square feet. It was conceived as a place of well-being and joy, bringing together movement activities, student support spaces, and dining in a building active almost around the clock.

530_DG_0000_New-Focal-Point

530_DG_0000_New-Focal-Point

530_DG_0000_Programm_Well-Beeing_Joy

530_DG_0000_Programm_Well-Beeing_Joy

We looked for a sustainable way to work with the existing building, as the college was open to adaptive reuse. Our study showed that the upper, obstructive portion needed to be removed, while the lower two levels — too constrained for larger student-center spaces — could accommodate the dining hall. We therefore proposed removing the upper floors to expose the existing concrete structure.

530_DG_0000_Merrill-Mcguire_remove-Top

530_DG_0000_Merrill-Mcguire_remove-Top

530_MO_0000_Beams-Post-Tension

530_MO_0000_Beams-Post-Tension

530_CI_0000_VIew-1

530_CI_0000_VIew-1

530_CI_0000_View-2

530_CI_0000_View-2

530_CI_0000_View-3

530_CI_0000_View-3

530_CI_0000_View-4

530_CI_0000_View-4

We introduced a new “table” defining the line between the old and the new, with a lightweight timber structure above housing the main student-center program. Taking advantage of the diagonal approach through the site, we established a central living room connecting to the corner historically known as “the beach,” with a ramped landscape leading through the building toward the dining hall and outside.

530_CI_0000_Wooden-Structure

530_CI_0000_Wooden-Structure

530_DG_0000_Access-Points_Student-Center

530_DG_0000_Access-Points_Student-Center

530_DG_0000_Acces-Points_Dining

530_DG_0000_Acces-Points_Dining

In November 2020, a letter from college president Biddy Martin set out a broader vision for the student centre, focused on atmosphere rather than simply rooms: light, views, activity, food, and a fluid relationship between inside and outside. We retained the earlier concept but shifted its focus to a central gathering point — the Crossroads Lounge — connected by an internal street, the Hangout Boulevard. A large central “table” forms the gathering floor beneath a broad roof, with smaller timber pavilions above.

530_DR_0000_Merrill-McGuire-Footprint

530_DR_0000_Merrill-McGuire-Footprint

530_DG_0000_Ways

530_DG_0000_Ways

530_DG_0000_Connecting-Parts

530_DG_0000_Connecting-Parts

530_DG_0000_Connecting-SEC

530_DG_0000_Connecting-SEC

530_DG_0000_Existing-Grid

530_DG_0000_Existing-Grid

530_DG_0000_Plaza

530_DG_0000_Plaza

530_DG_0000_Big-Roof

530_DG_0000_Big-Roof

530_DG_0000_Mass-Timber_Concrete_Line-1

530_DG_0000_Mass-Timber_Concrete_Line-1

The building has four levels and two entrances: Level 1 connects to the greenway, while the principal entrance from the quad is at Level 3. The opened-up former Merrill-McGuire block frames views toward the mountains, entrance, plaza, and terraces. The entrance leads to the Crossroads Lounge, which links the living room, “beach,” and event spaces. A courtyard brings daylight into the deep plan. Meeting spaces cluster around this central core, while offices sit toward the perimeter. Level 4 includes the Den Lounge, prayer room, dance spaces, theatre, student group spaces, and outdoor areas.

530_CI_0000_View-Access

530_CI_0000_View-Access

530_DR_0000_L3

530_DR_0000_L3

530_CI_0000_Foyer

530_CI_0000_Foyer

530_CI_0000_Lounge

530_CI_0000_Lounge

530_DR_0000_L3_2

530_DR_0000_L3_2

530_CI_0000_View-Restaurant

530_CI_0000_View-Restaurant

530_DR_0000_L4

530_DR_0000_L4

530_DR_0000_Group-Movement

530_DR_0000_Group-Movement

530_CI_0000_Interior

530_CI_0000_Interior

530_CI_0000_Theater

530_CI_0000_Theater

Level 2, within the existing concrete structure, contains the dining commons, kitchen, and back-of-house areas. With approximately 900 seats, it offers varied food options and dining settings. Level 1 contains the greenway entrance, with games, a grab-and-go shop, seating, and vending beneath the stairs, as well as a maker space, music rooms, radio station, mailroom, staff offices, and an alumni pub. The rough character of the existing concrete was retained where possible, with new additions deliberately blurring the distinction between old and new.

530_DR_0000_L2

530_DR_0000_L2

530_CI_0000_Concrete-Stair

530_CI_0000_Concrete-Stair

530_CI_0000_Restaurant-1

530_CI_0000_Restaurant-1

530_CI_0000_Restaurant-2

530_CI_0000_Restaurant-2

530_CI_0000_Columns

530_CI_0000_Columns

530_DR_0000_L1

530_DR_0000_L1

530_CI_0000_Concrete-Stair_2

530_CI_0000_Concrete-Stair_2

530_CI_0000_Entrance-1

530_CI_0000_Entrance-1

530_CI_0000_Alumni-Pub

530_CI_0000_Alumni-Pub

Student well-being drove the program and is part of Amherst’s wider sustainability agenda. Connected to the campus energy plant, geothermal systems, and grid, the fully electric building is designed to make its environmental strategies visible to students. Retaining part of the Merrill-McGuire structure saves approximately 1,900 tonnes of embodied carbon, while operational emissions are projected to be reduced by around 93% over 60 years. Solar generation, native planting, terraces, and on-site stormwater retention further support energy, biodiversity, and water-management goals.

530_DG_0000_Amherst-Climate-Action-Plan

530_DG_0000_Amherst-Climate-Action-Plan

530_DG_0000_Embodied-Carbon-1

530_DG_0000_Embodied-Carbon-1

530_DG_0000_Embodied-Carbon-2

530_DG_0000_Embodied-Carbon-2

530_DG_0000_Embodied-Carbon-3

530_DG_0000_Embodied-Carbon-3

530_DG_0000_Operational-Carbon-Emissions

530_DG_0000_Operational-Carbon-Emissions

530_DG_0000_PV-Energy-Generation

530_DG_0000_PV-Energy-Generation

530_DG_0000_Biodiversity

530_DG_0000_Biodiversity

530_DG_0000_Window-Wall-Ratio

530_DG_0000_Window-Wall-Ratio

The window-to-wall ratio and large overhangs were carefully designed to limit solar gain and reduce energy use. The building is entirely clad in wood, using a double-grid facade system developed in response to the constraints of the existing structure. The upper levels use lightly oiled Western Red Cedar, while the lower levels use the same timber with a near-black stain that takes on an eggplant tone in sunlight. “Eyelid” elements reduce the apparent size of openings while maintaining seated views and providing surfaces for display and other interior uses.

530_DG_0000_Facade-Timber-Cladding

530_DG_0000_Facade-Timber-Cladding

530_SA_0000_Facade-Timber-Color-Test

530_SA_0000_Facade-Timber-Color-Test

530_DG_0000_Dining-Seating_L2

530_DG_0000_Dining-Seating_L2

530_DR_0000_Exterior-Wall_ELE_SEC

530_DR_0000_Exterior-Wall_ELE_SEC

The lower levels retain the existing concrete structure; at Level 2, approximately two-thirds of the columns were cut to establish a consistent height. Above, the new structure becomes mass timber, with a “transfer table” carrying the timber grid onto the irregular existing concrete grid. The key challenge was reconciling precisely fabricated timber components with concrete columns that varied in size and position. Custom structural capitals and puzzle-like mechanical connections centre the loads, accommodate tolerances, and avoid exposed metal connectors. The timber was fabricated in Canada and delivered in installation sequence for assembly as a kit of parts.

530_DG_0000_Structure-Process

530_DG_0000_Structure-Process

530_DG_0000_Mass-Timber_Concrete_Line-1

530_DG_0000_Mass-Timber_Concrete_Line-1

530_DG_0000_Mass-Timber_Concrete_Line-2

530_DG_0000_Mass-Timber_Concrete_Line-2

530_CO_0000_001

530_CO_0000_001

530_CO_0000_002

530_CO_0000_002

530_CO_0000_003

530_CO_0000_003

530_CI_0000_Structure-Concrete-Wood

530_CI_0000_Structure-Concrete-Wood

530_DG_0000_Column-Joints

530_DG_0000_Column-Joints

530_DG_0000_Mass-Timber_Concrete_Joints

530_DG_0000_Mass-Timber_Concrete_Joints

530_CO_0000_004

530_CO_0000_004

530_DR_0000_Sasaki-Silman_Wood-Concrete-Joints

530_DR_0000_Sasaki-Silman_Wood-Concrete-Joints

Construction began by carving out the existing building and demolishing unnecessary portions, followed by the beam-by-beam assembly of the new mass-timber structure. Extensive mechanical, electrical, and plumbing systems were integrated, particularly for the kitchen and dining areas. Unexpected elements uncovered during construction were, in some cases, retained in their raw condition rather than concealed. Once the timber structure was complete, the facade was installed. The concrete staircase was cast afterwards, requiring careful coordination to avoid damaging the finished timber.

530_SI_0000_Merrill

530_SI_0000_Merrill

530_CO_0000_016

530_CO_0000_016

530_CO_0000_005

530_CO_0000_005

530_CO_0000_006

530_CO_0000_006

530_CO_0000_007

530_CO_0000_007

530_CO_0000_008

530_CO_0000_008

530_CO_0000_009

530_CO_0000_009

530_CO_0000_010

530_CO_0000_010

530_CO_0000_017

530_CO_0000_017

530_CO_0000_011

530_CO_0000_011

530_CO_0000_012

530_CO_0000_012

530_CO_0000_013

530_CO_0000_013

530_CO_0000_014

530_CO_0000_014

530_CO_0000_015

530_CO_0000_015

Drawings

530_DR_260914_Graphic-Set_SITE-PLAN

530_DR_260914_Graphic-Set_SITE-PLAN

530_DR_260914_Graphic-Set_L4

530_DR_260914_Graphic-Set_L4

530_DR_260914_Graphic-Set_L3

530_DR_260914_Graphic-Set_L3

530_DR_260914_Graphic-Set_L2

530_DR_260914_Graphic-Set_L2

530_DR_260914_Graphic-Set_L1

530_DR_260914_Graphic-Set_L1

530_DR_260914_Graphic-Set_SEC-1

530_DR_260914_Graphic-Set_SEC-1

530_DR_260914_Graphic-Set_SEC-2

530_DR_260914_Graphic-Set_SEC-2

530_DR_260914_Graphic-Set_ELE-NORTH

530_DR_260914_Graphic-Set_ELE-NORTH

530_DR_260914_Graphic-Set_ELE-EAST

530_DR_260914_Graphic-Set_ELE-EAST

530_DR_260914_Graphic-Set_ELE-SOUTH

530_DR_260914_Graphic-Set_ELE-SOUTH

530_DR_260914_Graphic-Set_ELE_WEST

530_DR_260914_Graphic-Set_ELE_WEST

Team

Facts

Client
Amherst College
Planning
Executive Architect : Sasaki Associates Inc., Massachusetts, USA
Executive Architect - Concept Phase: Beyer Blinder Belle Architects & Planners LLP, New York, USA
Structural Engineering: TYLin, New York, USA
Civil Engineering: Nitsch Engineering, Massachusetts, USA
Code Consultant: Cosentini Consulting & Fire Engineering, Massachusetts, USA
Cost Consultant: Dharam Consulting, New York, USA
Cost Consultant: Vermeulens Cost Consultants, Massachusetts, USA
MEP Engineering - Concept Phase : Buro Happold Engineering, Massachusetts, USA
MEP Engineering: BR+A Consulting Engineers, Massachusetts, USA
Facade Consultant: Front, New York, USA
Landscape architect: Stimson Studio, Massachusetts, USA
Lighting Consultant: Fisher Marantz Stone Partners, New York, USA
Specialist / Consulting
AV / Acoustic Consultant: Acentech Inc, Massachusetts, USA
Building Commissionning Agent : Wiss Janney Elstner Associates, New York, USA
Concrete Consultant: Reg Hough Associates LLC, New Jersey, USA
DIgital Rendering: Xaos Gmbh, Basel, Switzerland
Digital Rendering: Aron Lorincz Ateliers, Budapest, Hungary
Facade Engineering: RDH Building Science, Massachusetts, USA
Environmental and Geotechnical Consultant: Haley & Aldrich, Connecticut, USA
Food Service Consutant: Cromwell Consulting Inc., Massachusetts, USA
IT Consultant: Salas O' Brien, Massachusetts, USA
Signage: Yorgo&Co, Paris, France
Sustainability Consultant: Buro Happold Engineering, Massachusetts, USA
Sustainability Consultant - Concept Phase: Introba, Connecticut, USA
Telecommunication & Security: Sales O’Brien, Massachusetts, USA
Contractors
CM at Risk: Shawmut Design and Construction, Massachusetts, USA
Carpentry: Starlite Building Services Inc, New York, USA
Ceiling: American Contractors Corp, Massachusetts, USA
Concrete: Capasso Enterprises Inc, Connecticut, USA
Electrical: Universal Electric Company Inc, Massachusetts, USA
Elevator: Stanley Elevator, Connecticut, USA
Facade - Doors: Dawson Doors, New York, USA
Facade - Glazing: W&W Glass Products, New York, USA
Facade - Glazing: Tvitec, LeĂłn, Spain
Facade - Timber Cladding: Canadian Bavarian Millwork Lumber Ltd, Chemainus, Canada
Facade Manufacturing & Engineering: Chandler Architectural Products, Massachusetts, USA
Finish / Carpentry: Sweeney Drywall Finishes, Massachusetts, USA
Fire Protection: Wolverine Fire Protection, Connecticut, USA
Fire Rated Door: Willco Sales & Services, Connecticut, USA
Food Service Equipment: Johnson-Lancaster & Associates Inc, Florida, USA
Food Service Supplier: RPI Industries, New Jersey, USA
Landscape: Mountain View Landscapes & Lawncare, Massachusetts, USA
Mass Timber Fabrication & Engineering: Nordic Structures, Quebec, Canada
Millwork: Legere Group, Connecticut, USA
Millwork - Installer: Archer Corp, Massachusetts, USA
Millwork - Installer: Pursuit Construction, Connecticut, USA
Misc Metal: Mid State Welding Inc, Massachusetts, USA
Prefab Concrete: Coreslab Structures, Connecticut, USA
Roofing: Titan Roofing, Massachusetts, USA
Signage: Takeform, New York, USA
Signage: Artfxsigns, Connecticut, USA
Waterproofing: Armani Restoration, Connecticut, USA
Special Collaborators
Signage: Yorgo&Co, Paris, France
FF&E: Thos Moser, ME, USA
Building Data
Site Area: 178'380 sqft, 16'572 sqm
Gross floor area (GFA): 144'224 sqft, 13'398 sqm
Net floor area: 96'663 sqft, 8'980 sqm
Number of levels: 4
Footprint: 61'380 sqft, 5'702 sqm
Length: 245 ft, 74 m
Width: 253 ft, 77 m
Height: 58 ft, 17 m
Gross volume (GV): 526'792 cbft, 14'917 cbm
Facade surface: 39'194 sqft, 3'641 sqm